120 W Government (Imperium)
New construction for mixed-use, 3 story building in the historical district of downtown Pensacola. Work includes demolition and removal, site improvements, foundations, framing, exterior finishes, fire sprinkler, elevators, and interior finishes.
Jefferson Street Entry
Demolition, civil relocations, and renovation, exterior second-floor entry, elevator and elevator core, balcony and roofing to the historic downtown building.
Engineered Cooling Services
Demolition, civil relocations, and renovation, addition and interior finishes for office/warehouse building. Phase 3 of multiple contracted projects and work during the operation of initial phases.
Blount Building Headquarters
Major interior renovations to historic buildings. This was for class A leased office spaces and the building owner’s business offices and included high-grade woodwork and finishes, common area bath renovations and common hallway work. Work was coordinated with multiple general contractors on-site with adjacent businesses in operation.
White Sands Electric
New construction of a new 22,000 sf office and warehouse facility from ground up. Work includes site work, Concrete, steel, roofing, finishes, mechanical, electrical, plumbing.
DSGOGO
Renovation of a historical structure and expansion for architectural and real estate offices. Work included site work, selective demolition, foundations, slab on grade, wood trusses, interior finishes, landscaping, utilities, roofing, and owner equipment. This project was acknowledged by AIA NW Florida award for work complete in 2016.
Michles & Booth
New Law Offices of Michles & Booth, P.A.. Shallow foundations, structural block, slab on grade, steel bar joists and deck, single ply roofing, curtain wall glass system, full mechanical, electrical and plumbing, fire sprinkler, elevator and extensive interior finishes. Work also includes, site improvements, mass grading, hard and soft landscaping.
Baylen Lofts
This project is a classic warehouse to residential loft renovation. The work was the remodeling the old Bill Thompson Office Equipment on Baylen Street to 5ea town houses. Work consists of shoring the existing building to receive new steel frame, securing the new frame to the existing building, elevated concrete slabs, stairwells, separate service utilities, stairwells, framed 3rd floor, unit fire separation, exterior balconies, new single ply roofing, exterior finishes, garage doors, entry doors, glass and glazing, hurricane shutters, extensive underground utility work and new sidewalks and driveways.
Saltmarsh, Cleveland & Gund
Interior and exterior renovation and structural repair to accounting office. Work included: Structural repair, roofing, framing, block and brick, elevator, stairwells, interior finishes, geothermal HVAC system, electrical, fire sprinkler, plumbing. This project was contracted under a team, design /build approach.
Gulf Coast Community Bank
Relocation of a temporary bank building from Pea Ridge to 9-mile road. Work included: Site improvements, paving, landscaping, interior remodel. This project was contracted under a team, design/build approach
East Heights Plaza
Removal and replacement of blowout floor of beach 10-unit town house. Work included: Fill dirt, demolition, slab on grade, stairwells, wood framing, decks, drywall, utilities, stucco, coatings, railings, metal roofing and asphalt drives.
717 South Palafox
Structural repair and cleanup of a historical building in Pensacola, Florida. Work includes soil stabilization, structural repair, masonry repair, selective demolition, floor slab and utility services.
L&N Federal Credit Union
New one -story addition. Monolithic turned down slab, brick veneer, wood framed construction, pre-manufactured wood trusses, composition shingles and interior improvements.
Jefferson Street Apartments
Renovation of residential units in Historic district of downtown Pensacola.